| Release Date | May 19, 2026 |
|---|---|
| Release Owner | Donal Meehan |
| Corresponding ESR releases | 140.11.0 |
| Nightly cycle length | 4 weeks |
| Beta cycle length | 4 weeks |
| Milestones | |
|---|---|
Deadline to request manual QAQA has been informed via a Jira ticket (Functional, Nimbus/Remote delivery or Embedded QA) about features needing manual testing — more on how to file a Jira ticket here. Test Plans and Cases also require the technical documentation, which should be attached to the ticket. |
March 20 In 3 weeks |
Deadline to request accessibility engineering reviewAccessibility engineering review has been requested (using the |
March 20 In 3 weeks |
Nightly startsThe first day of the cycle is Merge Day. After merging mozilla-central to mozilla-beta, we bump the nightly version number on mozilla-central and a new development cycle starts for Firefox. A new Firefox Nightly is shipped every 12 hours. |
March 23 In 3.5 weeks |
Build ready for QAFeatures with a QA request are ready for testing to assess feature quality and provide a formal test report by the end of Week 2 of the nightly cycle. |
April 3 In 5 weeks |
QA Test Plan approval dueThe QA team appreciates an earlier sign-off from the project teams. The approval milestone will be the final deadline for any feature Test Plan sign-offs. No feedback/sign-off on QAs Feature Test Plan could result in misalignment on testing scope, incomplete test coverage and invalid bugs. |
April 3 In 5 weeks |
Draft beta release notesA draft document was created and shared internally with stakeholders to prepare our final release notes for general availability. This document initially contains a copy of our public beta release notes shipping the week after and will be enriched during the beta cycle with media and final copy. |
April 15 In 7 weeks |
String Freeze startsIn order to ensure that our localizers have adequate time to translate strings, please make sure that all string changes have landed by end of day. |
April 17 In 7 weeks |
QA pre-merge regression testing doneQA assess build readiness for shipping to Beta by running a set of Regression test cases and shares a test report. |
April 17 In 7 weeks |
Merge dayThis is the day in the release cycle when we merge mozilla-central into mozilla-beta. This is the end of the development cycle for Firefox 151 and the beginning of our Beta stabilization cycle. |
April 20 In 7.5 weeks |
Beta 1Rolled out to 50% of our beta population. Some experimental features are still activated to watch their behavior on a wider population. These experimental features will be deactivated mid-cycle. |
April 22 In 8 weeks |
Beta 2First automated beta of the cycle. It is rolled out to 100% of our beta population. Build starts at 13:00 UTC. |
April 24 In 8 weeks |
SUMO content creationUser affecting changes were identified and provided to the support.mozilla.org team. The support content for this release can now be created and will be translated before RC week. |
April 24 In 8 weeks |
Beta 3Build starts at 13:00 UTC. Stabilization work via uplifts. |
April 27 In 8.5 weeks |
Beta 4Build starts at 13:00 UTC. Stabilization work via uplifts. |
April 29 In 9 weeks |
Beta 5 Last early betaOn a regular 4 weeks beta cycle, Beta 5 is the last beta with experimental features still activated. Build starts at 13:00 UTC. Stabilization work via uplifts. |
May 1 In 9 weeks |
Beta 6Build starts at 13:00 UTC. Stabilization work via uplifts. Experimental features are no longer activated at compile time. |
May 4 In 9.5 weeks |
SUMO content localizationNew content on support.mozilla.org team is finalized, uploaded to the server and provided to our localization teams internationally. |
May 4 In 9.5 weeks |
Beta 7Build starts at 13:00 UTC. Stabilization work via uplifts. |
May 6 In 10 weeks |
Pre-release QA sign-offA week before the final sign-off, QA shares preliminary test reports for each feature riding the train. This pre-release sign-off can be Green, Yellow or Red. |
May 6 In 10 weeks |
Beta 8 Security bugs uplift request deadlineBuild starts at 13:00 UTC. Stabilization work via uplifts. |
May 8 In 10 weeks |
Beta 9Build starts at 13:00 UTC. Stabilization work via uplifts. |
May 11 In 10.5 weeks |
Release notes submission deadlineAll release notes for Firefox were added to the draft document or communicated directly with the release manager. Illustrations such as screenshots and videos were provided. Final Release release notes are created by the release manager on firefox.com. |
May 12 In 10.5 weeks |
Beta 10 Last beta upliftsOn a regular 4 weeks beta cycle, this is the last beta and thus the end of beta uplifts. Build starts at 13:00 UTC. |
May 13 In 11 weeks |
Release Candidate Go to buildWe merge our mozilla-beta repository to mozilla-release and close mozilla-beta until the next merge day. We then build our Release Candidate from mozilla-release. This is the build we intend to ship a week later unless we need to build another Release Candidate to fix a major quality or business critical issue. |
May 13 In 11 weeks |
Release Candidate Release notes finalizedOur Release Candidate is built and available for testing. |
May 13 In 11 weeks |
Release day!We ship Firefox 151 at 14:00 UTC (6AM PST) at 25% rollout. |
May 19 In 11.5 weeks |
Potential Android dot releaseOne week after the release, we evaluate shipping an Android dot release to address identified issues. We can also enable new features on a on a case by case basis if they are suitable for uplift. The decision on shipping or not this dot release for Android is on the release management team. |
May 26 In 12.5 weeks |
Planned dot releaseTwo weeks after the release, we ship a desktop and/or an Android dot release to address identified quality issues with safe fixes ready. We can also enable new features on a on a case by case basis if they are suitable for uplift. We may have to ship other dot releases before that date. If this is the case and post-release quality issues are already fixed and shipped, the decision on shipping or not the planned dot release is on the release management team. |
June 2 In 13.5 weeks |
| Milestones | |
|---|---|
151.0 branch is createdThe |
May 8 |
151.0 release candidate is createdThe 151.0 release candidate is created based on the |
May 8 |
Preliminary QA sign off on 151.0QA gives a preliminary sign off on 151.0. If it is green, we push the build to the External Beta Testers group. Otherwise, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 11 |
Final QA sign off on 151.0 Release notes readyQA gives its final sign off on 151.0. If the sign off is red, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 12 |
151.0 sent to Apple StoreWe submit 151.0 for review to the Apple Store. If we don`t have a working build by the end of the day, we may not ship this week. |
May 12 |
151.1 branch is createdThe |
May 15 |
151.1 release candidate is createdThe 151.1 release candidate is created based on the |
May 15 |
151.0 is shipped151.0 is shipped on the Apple Store at 3:00 AM UTC with a phased 7 days rollout: |
May 18 |
Preliminary QA sign off on 151.1QA gives a preliminary sign off on 151.1. If it is green, we push the build to the External Beta Testers group. Otherwise, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 18 |
Final QA sign off on 151.1 Release notes readyQA gives its final sign off on 151.1. If the sign off is red, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 19 |
151.1 sent to Apple StoreWe submit 151.1 for review to the Apple Store. If we don`t have a working build by the end of the day, we may not ship this week. |
May 21 |
151.2 branch is createdThe |
May 22 |
151.2 release candidate is createdThe 151.2 release candidate is created based on the |
May 22 |
151.1 is shipped151.1 is shipped on the Apple Store at 3:00 AM UTC with a phased 7 days rollout: |
May 25 |
Preliminary QA sign off on 151.2QA gives a preliminary sign off on 151.2. If it is green, we push the build to the External Beta Testers group. Otherwise, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 25 |
Final QA sign off on 151.2 Release notes readyQA gives its final sign off on 151.2. If the sign off is red, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
May 26 |
151.2 sent to Apple StoreWe submit 151.2 for review to the Apple Store. If we don`t have a working build by the end of the day, we may not ship this week. |
May 28 |
151.3 branch is createdThe |
May 29 |
151.3 release candidate is createdThe 151.3 release candidate is created based on the |
May 29 |
151.2 is shipped151.2 is shipped on the Apple Store at 3:00 AM UTC with a phased 7 days rollout: |
June 1 |
Preliminary QA sign off on 151.3QA gives a preliminary sign off on 151.3. If it is green, we push the build to the External Beta Testers group. Otherwise, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
June 1 |
Final QA sign off on 151.3 Release notes readyQA gives its final sign off on 151.3. If the sign off is red, the dev team fixes the issues reported by QA, uplift them to the release branch and we build another Release Candidate. |
June 2 |
151.3 sent to Apple StoreWe submit 151.3 for review to the Apple Store. If we don`t have a working build by the end of the day, we may not ship this week. |
June 4 |
151.3 is shipped151.3 is shipped on the Apple Store at 3:00 AM UTC with a phased 7 days rollout: |
June 8 |